Geological, environmental, cultural and design due diligence

  • Army Corps of Engineer's flood plain delineation published July 3, 2006.
  • Natural water retention requires no maintenance.
  • Jurisdiction delineation prepared for submittal February 3, 2006.
  • ALTA survey, pinned, and new legal description prepared March 23, 2006.
  • Topographical maps in 2' contours and available for construction in 1' contours March 23, 2006.
  • Title report prepared July 10, 2006.
  • Sewer permit applied for, submitted April 17, 2006, approved July 29, 2006.
  • Water permit applied for, submitted June 15, 2006, and approved July 27, 2006.
  • Archeological review completed July 7, 2006.
  • Phase I completed July 13, 2005.
  • Biological evaluation completed March 3, 2006.
  • Huachuca City General Plan traffic impact study dated July 22, 2002 was reevaluated July 3, 2006 including traffic signal plans, road width requirements, radius, and speed limits.
  • Campstone's infrastructure impact on Huachuca City completed June 8, 2006
  • Primary roads designed and detailed with cross sections and wash crossing, positioned and dusted in by GPS, and traffic distribution integration completed December 12, 2005.
  • Utility easements associated with private land completed March 1, 2006.
  • Air traffic evaluation completed June 13, 2006.
  • Industrial use evaluation completed June 13, 2006.
  • Hydrology completed March 30, 2004.
  • Project documented in Auto Cad 12.
  • Fee structure defined with Preliminary Plat and sewer fee paid July 29, 2006.
  • Neighbors within 300' identified May 8, 2006.
  • Preliminary plat submitted July 29, 2006.
  • Engineering and design standards identified and documented June 16, 2006.
  • Storm Water Pollution and Prevention Plan and NOI prepared December 5, 2005. Awaiting implementation of the sewer, water, and Mustang Road improvements.
  • Campstone's due diligence recorded in 16 books completed July 17, 2006.